Madrid–Malaga AVE reopening pushed back again

Madrid–Malaga AVE stay disrupted after landslide, with delays to late April and longer journeys hitting Easter trips to the Costa del Sol.
Madrid–Malaga AVE closure extended
NurPhoto Getty images

The Madrid–Malaga AVE high-speed line will remain disrupted for weeks longer than planned, with Spain’s rail infrastructure manager Adif confirming that direct services will not resume before the last week of April. 

The closure is extending journey times and clouding tourism expectations on the Costa del Sol ahead of Semana Santa (Holy Week).

What has happened on the Madrid–Malaga AVE line?

The interruption affects the high-speed section of the corridor near Álora, in Malaga province.

  • The line has been cut on this stretch since early February after severe weather damaged the infrastructure.
  • Initial reopening targets of 2 February, 7 February and then 23 March have all been missed.
  • The last week of April is now the earliest realistic date for restoring direct high-speed services between Madrid and Malaga.

Current Madrid–Malaga travel options

Bus–train transfers on the AVE corridor

While the Álora section is out of service, passengers travelling between Madrid and Malaga use a combined bus–train operation. 

High-speed trains run between Madrid and Antequera–Santa Ana, while buses cover the missing leg between Antequera–Santa Ana and Malaga.

What to expect once direct AVE services resume

Adif’s current plan for the corridor includes:

  • Direct AVE traffic resuming no earlier than the last week of April, subject to ongoing reviews and weather.
  • Initial running on a single track with speed restrictions over a short stretch at Álora.
  • A return to double-track running around June, once most of the demolition and slope work is complete.
Madrid–Malaga high-speed line
Cristina Arias Getty images

Tourism and economic impact on Malaga and the Costa del Sol

The prolonged disruption comes at a sensitive moment for Malaga’s tourism industry:

  • The Málaga Film Festival, which has just finished, typically draws visitors and film professionals who rely on the AVE from Madrid.
  • Semana Santa is one of the busiest times of year for hotels and rentals in Malaga and along the Costa del Sol.

Business groups report that longer and less predictable journeys are deterring some travellers and complicating advance bookings,

Madrid–Malaga AVE timeline

Date / period
Event
18 January
Initial issues and partial service disruptions on the Madrid–Malaga corridor.
4–5 February
Intense storms over Andalusia trigger a landslide and collapse of a 300‑metre retaining wall, cutting the high-speed section.
Early February
AVE services switch to a combined bus–train operation via Antequera–Santa Ana.
26 February
24‑hour repair works begin.
23 March
Initial target for partial reopening with one track is abandoned after engineers determine that remaining walls do not meet safety thresholds.
Last week of April (provisional)
New earliest reference point for restoring direct AVE traffic, subject to ongoing reviews.
Around June (indicative)
Expected point at which both tracks could be reopened in the Álora area following major demolition and slope works.
End of 2026
Current horizon for full structural repair, including replacement of the damaged track apparatus and a return to standard operation.